Hello SAP Gurus,
When I run CK11N to estimate the standard cost, I get the result only without the direct machine cost, but labor cost is correct as bellow:
http://scn.sap.com/servlet/JiveServlet/downloadImage/506810/image001.png
As you can see:
(1) the costing lot size is 1000PC
(2) direct machine cost (HMAC) is 0.00
When I check the relavant factors, I cannot find any errors:
(1) Activity price:KP26
http://scn.sap.com/servlet/JiveServlet/downloadImage/506811/image003.png
(2) Routing:CA23
http://scn.sap.com/servlet/JiveServlet/downloadImage/506812/image005.png
(3) work center: CR03
http://scn.sap.com/servlet/JiveServlet/downloadImage/506816/image007.png
According to the basic data I maintained, the direct labor cost=(70*1000PC/3600s)*200=3888.88, That is correct.
So the direct machine cost should be: (40*1000pc/3600s)*100=1111.11, but it is actually 0.00 now.
It seems no problem for every factor, I really don't know what causes the error which actually no error message. Could you please give me some advice to resolve it? Or do I missed some key configuration?
Thank you very much!
Eric